*To return the Plant to its 500,000MTPA nameplate capacity
WorldStage Newsonline– Notore Chemical Industries Plc said the Turn Around Maintenance (TAM) of it’s fertiliser plant has commenced and barring any unforeseen circumstance, it should be completed on 8th March 2021.
Notore in a notification at the Nigerian Stock Exchange said the objective of the TAM is to return the Plant to its 500,000MTPA nameplate capacity and improve the reliability index to 95%.
“Although disruption to global businesses occasioned by the COVID-19 pandemic and its attendant restrictions by Governments all over the world affected the timely delivery of procured spares and the arrival to site of Vendor Service Men (VSM), the TAM is still on course,” the notification said.
“Upon completion, we expect a significant improvement in the Plant’s reliability index and a sustained daily production output of 1,500MT.
“Attaining this level of production will guaranty improved cashflow, increase in annual revenue as well as return the Company to profitability.”